Home › How it works

How long does a fibreglass pool take?

About 6 to 8 weeks from deposit to delivery. The shell is set in a day or two, and the whole backyard usually takes one to three weeks. Add approval first, usually two to six weeks, and most pools are finished about 9 to 17 weeks after you lodge, so roughly two to four months. A pool is a big cheque to write to a business you found last week. So here is the whole process, week by week, with who does what at every step.

The short version

A fibreglass pool shell arriving on the trailer on delivery day
Delivery day. The shell comes off the truck and over the fence in one lift.

How long does a fibreglass pool take to install?

About 6 to 8 weeks from deposit to delivery. The shell is set in a day or two, and the whole backyard usually takes one to three weeks. Add approval first, usually two to six weeks, and most pools are finished about 9 to 17 weeks after you lodge, so roughly two to four months.

How long from deposit to delivery for a fibreglass pool?

About 6 to 8 weeks from deposit to shell on site. The factory sets the lead time, and you get the current number before you pay a deposit.

How long does pool approval take?

Usually two to six weeks for a complying development certificate. The engineering pack is free before you pay a deposit, so approval can run while you decide.

How long does it take to set a fibreglass pool shell?

A day or two. Backfill, plumbing, paving and the fence usually take another one to three weeks.

The timeline

Week by week, from approval to swim

The factory sets the lead time. It is about 6 to 8 weeks from deposit to shell on site. We tell you the factory’s current number before you pay a deposit, so the date on this timeline is a real one.

Fibreglass pool shell set in the ground, reinforcement laid for the bond beam
Set and levelled, before backfill, paving and water.

How the pool goes in, stage by stage

The install, stage by stage

This is the part your builder or trades do. Every kit comes with the engineered installation details for your shell, so they work to the numbers on paper. Here is what happens, and who does it.

Show all 9 stages, day by day
  • Before the dig

    Set-out and checks

    The pool is pegged out on the ground against the approved plan and the setbacks. Underground services are located through Before You Dig Australia, and the soil and water table are checked, because they decide the base and the backfill. Who: your builder or installer.

  • Day 1 to 2

    Excavation

    The hole is dug to the shell’s shape, a little wider and longer than the pool for working room, and slightly deeper than the finished floor to leave room for the base. Spoil is trucked away or kept for landscaping. Rock, clay and tight access are what stretch this stage. Who: an excavator operator.

  • Day 2

    The base

    A bed of crusher dust or fine crushed rock is spread, compacted and screeded dead level, with the slight fall the drawings call for. It is the most important line on the job: a true base means a true pool. Who: your builder or installer.

  • Delivery day

    The lift and the set

    The truck arrives and the shell is lifted off with a spreader bar, onto the driveway, straight into the yard, or over the house where the access needs it, and lowered onto the base. It is checked for level along the coping in both directions and adjusted until it sits true. Who: crane operator and installer. We confirm truck and crane access with you before the day.

  • Same week

    Plumbing connections

    The skimmer box, the return jets and the hydrostatic valve are built into the shell. A licensed plumber runs the suction and return lines to the equipment pad, fits the pump, filter and chlorinator, and runs the backwash line to a sewer gully, never to stormwater. Who: licensed plumber.

  • Same week

    Backfill and water together

    Water goes into the pool and backfill goes around it at the same time, rising together in stages so the walls are always pushed equally from both sides. The backfill material is what the engineering specifies for your ground. A temporary compliant fence goes up as soon as the pool holds water. Who: your builder or installer.

  • Week 2

    Bond beam and coping

    A steel-reinforced concrete beam is poured around the top of the shell. It locks the pool into the ground so it cannot move or lift. Once the concrete has cured, about a week, the coping and paving go on. Who: your builder, concreter and paver.

  • Week 2 to 3

    Power, barrier and inspection

    A licensed electrician runs a dedicated circuit to the equipment pad and connects the light. The permanent pool barrier goes up to the Australian Standard, the certifier inspects it, and the pool is registered on your state’s pool register. Who: licensed electrician, fencer, certifier.

  • Swim day

    Commissioning

    The equipment is started, the salt goes in, and the water is balanced with the test kit from the handover kit. We talk you through the chlorinator and filter settings on the phone. Who: you, with us on the line.

What moves the timeline and the cost. Access for the truck and crane, rock or wet ground in the dig, retaining walls, and how long approval takes. The shell is the easy part. That is why we look at your block before anyone puts a number on an install.

Delivery day, filmed on our jobs

Two clips from our jobs

No stock footage. These are our own jobs: the shell going up on the crane and over the house, then the backfill going in as the water rises.

Over the roof, no side access needed
Past the pergola and into the yard
Backfill goes in as the water rises

What is not in our price

Our delivered price is the shell, your equipment package, the engineering pack with your state's compliance certificate, and freight to your site, inc GST. It is fixed on your quote and nothing is added on top.

Excavation and spoil, rock if you hit it, the crane (and a road closure if one is needed), setting the shell, the bond beam, plumbing with its pipe and fittings, electrical, the approval, the pool fence, coping and paving, landscaping, and first fill water if it is not from mains.

On a typical Sydney block with no rock and a small crane, the dig to the bond beam usually lands between $20,000 and $28,000 on top of the kit. With power, a CDC, a fence and basic paving, most land between $38,000 and $55,000 plus the kit.

In Sydney and on the Central Coast our licensed crew can quote the install, after a site assessment. Everywhere else your own builder or installer quotes these, and your installer can call us with any questions. Every cost outside our price, with typical ranges and who supplies it.

What happens after you pay

Deposit, balance and refunds

This is the part people worry about when they are sending money to a business they found online, so here it is plainly.

The deposit$5,000 books your pool and your slot at the factory, and comes off your total. You pay it by card from your quote page or by bank transfer, and you get a receipt and your dates in writing.
If council or your certifier says noGet your approval sorted before you pay the deposit if you are not sure. The engineering drawings and certificate are yours to use for it, free. The deposit places your factory order, usually within a day or two. Before then you can change your mind for a full refund. Once your shell is in production it is non-refundable, unless we cannot supply your pool, in which case you get it back in full.
If you change the model or colourModel, size or colour can change free until the factory starts your shell. After that, a change is a new order.
The balanceDue 14 days before delivery, in cleared funds, by bank transfer. We confirm the delivery date before the balance is due, so you are never paying against a date that does not exist.
If the factory date movesWe tell you the moment we know. Your balance date moves with it. Lead time is about 6 to 8 weeks from deposit.
If your site is not readyTalk to us early. A shell can usually be held at the factory rather than delivered to a yard with no hole in it.
On delivery daySomeone needs to be on site to take the pool, and access needs to be clear for the truck and the crane.
After the water is inYou get the warranty documents, the equipment manuals and a handover walk-through of how to run it. Warranty questions come straight to us.

The full terms of supply are here, in plain words rather than fine print.

Who does what

Us, your builder, your certifier
Hull Pools, every jobShell, equipment package, engineering pack, state compliance certificate, freight, delivery day coordination, crane booking advice, answers to your certifier, answers for your installer.
Hull Pools, install jobsIn Sydney and on the Central Coast, our crew can install it, priced after a site assessment.
You, every jobCouncil or certifier approval, the safety barrier, the electrician, the final inspection and pool registration. We tell you when each one is due.
You or your builderExcavation, crane hire, the base, setting the shell, plumbing, backfill, bond beam and coping, with your own trades. The stages above, and the engineered details in the kit, lay it out.

The paperwork you get

Every document, listed
Money. Two payments: $5,000 to book, and the balance 14 days before delivery. Nothing else. The full terms of supply are here in plain words.
Finished fibreglass pool at Collaroy at dusk
Collaroy. Swim day.

Want your dates on this page?

Tell us the model and your suburb. One delivered number, then this timeline with your weeks filled in.

Get my price

Or call Will on 0415 140 001

IncludedWhat runs your poolGuideSupply only, what you getGuideDelivery & accessProofRecent jobs
CallGet my price